Major Capital Projects (also called Major Caps) include new construction and substantial alterations, extensions, or improvements to existing structures with an estimated cost in excess of $1 million.  Depending on the source of funds and the estimated project cost, Major Caps may require review and approval by the Campus Planning Committee, the Chancellor, the Office of the President, and/or the Board of Regents.  The Budget and Planning Office manages the planning and approval process for Major Caps.

 

 

The Consolidated Capital Report (CCR) is the University of California systemwide strategic planning document for capital improvement projects. Covering a 6-year window, the CCR summarizes each campus’ capital needs, in alignment with the UCSB Long-Range Development Plan, Academic Plan, and Physical Design Framework.

 

General Summary of Required Approvals

Multiple variables factor into the necessary approval path for any project.  The campus recommends early consultation with the Capital Development team to determine the appropriate level of review.

  • Projects over $70 million and all State funded projects require review and approval by the UC Boards of Regents.
  • The UC Office of the President’s delegated authority may approve Non-State funded Projects under $70 million that are included in the Capital Financial Plan (CFP).
  • The Chancellor’s delegated authority may approve Non-State funded projects under $20 million that are included in the CFP and have a UCOP-approved Project Planning Guide (PPG).
  • The Chancellor’s delegated authority may approve Non-State funded projects under $10 million (“Mini-majors”) that are included in the CFP without a PPG.

 

CPC Level of Review form

Major Capital Approval form

Current Projects

ProjectBudgetStatus
Campus Access Controls Improvements$900,000Complete
Music Building Unit 1 Seismic Improvements$15,000,000Complete
North Campus Faculty Housing Phase IV and V (Ocean Walk)Public-Private PartnershipComplete
Sara Miller McCune Arts Library Renovation$2,465,000Complete
UCen 1 Roof Replacement$1,277,000Complete
Ellwood Marine Terminal Demolition and Restoration$19,850,000Construction
Fueling Station & Wash Bay Relocation$2,076,334Construction
KITP (Kavli Institute for Theoretical Physics) House$77,000,000Construction
Psychology Brain Sciences 3rd Floor Renovation$1,493,000Construction
San Benito Student Housing$624,400,000Construction
Santa Cruz Island Reserve Phase 1 Housing$2,681,143Construction
East Campus Student Housing$566,058,000Pre-Construction
Mesa Parking Structure 18 Elevators 1 & 2 Refurbishment$999,000Design
Chemistry Building Seismic Improvements$4,000,000Planning
Childcare Facility Expansion$43,931,808Planning
Devereux Environmental Crossroads$23,000,000Planning
Eddleman Quantum Institute$190,000,000Planning
Engineering II Pavilion Addition / Auhll Robotic Laboratory$7,846,515Planning
Ocean Road Faculty and Staff HousingTBDPlanning
Ocean Science Education Building Phase IITBDPlanning
Engineering III Building$224,400,000On Hold
Marine Biotechnology Lab$255,000,000On Hold
New Physics Building$224,400,000On Hold
UCEAP Devereux$9,000,000On Hold
 

Past Projects

ProjectBudgetCompleted
Chemistry Building Cryo Lab$1,238,0002024
Bike Shop$3,200,0002023
Classroom Building (Interactive Learning Pavilion)$97,130,0002023
Events Center End Courts Seating Replacement$1,917,0002023