Major Capital Projects (also called Major Caps) include new construction and substantial alterations, extensions, or improvements to existing structures with an estimated cost in excess of $1 million.  Depending on the source of funds and the estimated project cost, Major Caps may require review and approval by the Campus Planning Committee, the Chancellor, the Office of the President, and/or the Board of Regents.  The Budget and Planning Office manages the planning and approval process for Major Caps.

 

 

The Consolidated Capital Report (CCR) is the University of California systemwide strategic planning document for capital improvement projects. Covering a 6-year window, the CCR summarizes each campus’ capital needs, in alignment with the UCSB Long-Range Development Plan, Academic Plan, and Physical Design Framework.

 

General Summary of Required Approvals

Multiple variables factor into the necessary approval path for any project.  The campus recommends early consultation with the Capital Development team to determine the appropriate level of review.

  • Projects over $70 million and all State funded projects require review and approval by the UC Boards of Regents.
  • The UC Office of the President’s delegated authority may approve Non-State funded Projects under $70 million that are included in the Capital Financial Plan (CFP).
  • The Chancellor’s delegated authority may approve Non-State funded projects under $20 million that are included in the CFP and have a UCOP-approved Project Planning Guide (PPG).
  • The Chancellor’s delegated authority may approve Non-State funded projects under $10 million (“Mini-majors”) that are included in the CFP without a PPG.

 

CPC Level of Review form

Major Capital Approval form

Current Projects

Project Budget Status
Campus Access Controls Improvements $900,000 Complete
Sara Miller McCune Arts Library Renovation $2,465,000 Complete
UCen 1 Roof Replacement $1,277,000 Complete
Ellwood Marine Terminal Demolition and Restoration $19,850,000 Construction
Fueling Station & Wash Bay Relocation $2,076,334 Construction
Music Building Unit 1 Seismic Improvements $15,000,000 Construction
North Campus Faculty Housing Phase IV and V (Ocean Walk) Public-Private Partnership Construction
Psychology Brain Sciences 3rd Floor Renovation $1,493,000 Construction
Santa Cruz Island Reserve Phase 1 Housing $1,981,143 Construction
East Campus Student Housing $640,000,000 Design
Mesa Parking Structure 18 Elevators 1 & 2 Refurbishment $999,000 Design
San Benito Student Housing $624,400,000 Design
Chemistry Building Seismic Improvements $4,000,000 Planning
Childcare Facility Expansion TBD Planning
Devereux Environmental Crossroads TBD Planning
Eddleman Quantum Institute $190,000,000 Planning
Marine Biotechnology Lab $62,000,000 Planning
Ocean Science Education Building Phase II TBD Planning
UCEAP Devereux TBD Planning
Engineering III Building TBD On Hold
Music Renewal TBD On Hold
New Physics Building TBD On Hold
Ocean Road Faculty and Staff Housing Public-Private Partnership On Hold
 

Past Projects

Project Budget Completed
Chemistry Building Cryo Lab $1,238,000 2024
Bike Shop $3,200,000 2023
Classroom Building (Interactive Learning Pavilion) $97,130,000 2023
Events Center End Courts Seating Replacement $1,917,000 2023